Date on which a break in a stormwater pipe beneath a coal ash disposal pit at a shuttered Duke Energy power plant near Eden, N.C. contaminated the Dan River with toxic coal ash: 2/2/2014
Estimated tons of coal ash -- which contains toxins including arsenic, lead, mercury, and radioactive elements -- that were released to the river: 50,000 to 82,000
Number of Olympic-size swimming pools that amount of coal ash would fill: 20 to 32
Estimated gallons of coal ash-contaminated water from the storage pit that also reached the river: 24 million to 27 million
Number of rail cars the toxic pollution could fill: 413 to 677
Rank of the spill among the largest coal ash spills in U.S. history: 3
Hours that Duke Energy waited from the time it discovered the spill to report it to the public: 26
Miles downstream of the spill site that Danville, Va. draws its drinking water: 6
Age in years of Duke Energy's Dan River ash pits: 53
Year in which Environmental Protection Agency (EPA) inspections found problems with leakage at the plant's coal ash dam as well as dilapidated and poorly maintained stormwater pipes: 2009
Number of coal-fired power plants that Duke Energy owns across North Carolina: 14
Percent of those plants where there have been unpermitted discharges of coal ash to the environment: 100
Amount that is being spent to run a municipal water line to the North Carolina community of Flemington because a leaky Duke Energy coal ash pit contaminated the local groundwater supply: $2.25 million
Amount of that total cost being borne by the local community: $472,000
Number of times more likely someone living near a coal ash pit is to develop cancer than someone who smokes a pack of cigarettes a day: 9
Year in which the EPA administrator pledged to enact the first-ever federal regulations of coal ash disposal: 2009
Year in which public health and environmental advocacy groups sued the EPA over its failure to enact the promised regulations amid pressure from Duke Energy and other coal-burning power companies: 2012
Amount Duke Energy spent on federal lobbying last year alone, including on efforts to block strict coal ash regulations: $5.99 million
Date on which the Department of Justice lodged a consent decree requiring EPA to release a final coal ash rule: 1/29/2014
Date by which the EPA must publish the final rule on coal ash disposal: 12/19/2014
(Click on figure to go to source.)